• Construction of a new Sewerage Pump station as well as associated Gravity and Rising Main pipelines.
• Project was phased over 2 years as funding became available.
• Pump station to deliver a flow rate of 135 ?/s
MOSSEL BAY MUNICIPALITY
R 13,46 million (VAT incl)
GREAT BRAK RIVER
July 2016 - June 2019 (36 months)